An Ideal Golf Course Development Timeline

  • Site analysis and information gathering (up to 30 days)
    Preliminary routing plans and studies (up to 30 days)
  • Final routing plans after eliciting Owner's recommendations & critiques
  • Construction drawings and construction specifications (90-120 days)
  • Construction bidding (up to 30 days)
  • During these early stages, behind the scenes engineering takes place to obtain the necessary permits. *acquisition of permits not figured during this time*.
  • Begins with Breaking Gorund in the peak season geographically (timed to meet grassing window; typically 6 months - 1 year)
  • Grassing/Grow-In (typically 3-6 months)
 